Wellbeing Hub, Weston General Hospital
Client:
University Hospitals Bristol & Weston Trust
Value:
£500k
Programme:
12 Weeks
Overview
We were appointed to deliver the creation of new SEMH (Social, Emotional and Mental Health) facilities at Weston General Hospital, transforming a former nursery space into a modern, supportive environment.
The project involved internal and external refurbishment works to create a range of functional spaces, including kitchen, breakout and relaxation areas. Delivered within a live hospital setting, the programme was carefully managed to ensure works were completed efficiently and handed back ahead of schedule.
A key feature of the scheme was the use of our in-house carpentry team to supply and install bespoke furniture, supporting both programme and quality outcomes.

Scope of work
- Full strip-out of existing spaces
- Formation of kitchen, breakout and relaxation areas
- Installation of bespoke furniture by in-house carpentry team
- Installation of vinyl flooring, Whiterock wall finishes and feature wall elements
- Ceiling replacements and full internal redecorations
- Removal and reinstatement of mechanical and electrical services
- Upgrades to lighting, power and ventilation systems
- Refurbishment of circulation spaces
- Upgrades to existing WC and DDA WC facilities
- Replacement flooring, ceilings and decorations throughout