Overview
Following appointment through a competitive tender process, we delivered the replacement of an ageing and failing heating pipework system across a live school campus, alongside the refurbishment of two WC areas within the summer holidays.
The project combined complex infrastructure upgrades with internal refurbishment works, all delivered within a tight programme to ensure the school could return to full operation without disruption.
By carefully managing sequencing, and leveraging our directly employed foreman and in-house interiors team, the programme was accelerated — successfully condensing a 10-week scope of works into the 8-week summer holiday window.
Scope of work
- Full replacement of existing threaded steel heating pipework across the main school building
- Associated asbestos removal works
- Ceiling replacement works
- Passive fire protection upgrades
- LED lighting installation
- Fire alarm works
- Associated internal decorations
- Full strip-out of existing WC facilities
- Reconfiguration from split-sex layout to open plan same-sex arrangement
- Installation of new sanitaryware and IPS systems
- Installation of solid partition cubicles
- Whiterock wall finishes and vinyl flooring